PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

DOWNTOWNMahaRERA P52100018235

by SAMARTTHA BUILDCON

SR NO 6, MAHALUNGE, 411045

Sept 2026
Possession
81.6%
Built
7
Complaints
71
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Apr 2022, now proposed Sept 2026 per the RERA filing.
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2026 per the RERA filing.

Official RERA facts

Registration
P52100018235
Status
New
Stage
Certificate Signed
Possession
September 2026originally April 2022
Construction
81.6% complete
Units sold
34 of 71

RERA complaint record7 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths90%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingnot started
Community Buildings75%
Water conservation /Rain water harvestingdone
Energy managemcntdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Oct 2018
Floors
5
Unit mix
71 res ยท 0 comm
Architect
SWAPNIL P KSHIRSAGAR

Buyer community

Connect with other buyers and owners of DOWNTOWN โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching DOWNTOWN. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.