Under construction

DESHMUKH ARCADEMahaRERA P52100018597

by JAY DESHMUKH CONSTRUCTION

247, DESHMUKH WASTI, 413102

Dec 2028
Possession
55.2%
Built
0
Complaints
43
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Oct 2024, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P52100018597
Status
New
Stage
Certificate Signed
Possession
December 2028originally October 2024
Construction
55.2% complete
Units sold
20 of 43

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths10%
Water Supply25%
Sewerage (Chamber, Lines, Septic Tank , STP)25%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Nov 2018
Floors
8
Unit mix
29 res ยท 14 comm

Buyer community

Connect with other buyers and owners of DESHMUKH ARCADE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching DESHMUKH ARCADE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.