PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Playtor Paud D- Phase 2MahaRERA P52100018651

by SANGAM REALTY

Gat No 272, Next to Tehsil Office, 412108

Sept 2026
Possession
0%
Built
0
Complaints
0
Units
High risk
  • Behind schedule. Possession is due Sept 2026 but construction is only at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2026 per the RERA filing.

Official RERA facts

Registration
P52100018651
Status
New
Stage
Certificate Signed
Possession
September 2026
Construction
0% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Retaining Wallnot started
Earthworknot started
Compound Wallnot started

Building & registration

RERA registered
Nov 2018
Floors
8

Buyer community

Connect with other buyers and owners of Playtor Paud D- Phase 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Playtor Paud D- Phase 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.