VISION BOULEVARD - Phase IIMahaRERA P52100018670

by VISION HOME PROJECT

S No 76/2A,77/1,77/2, CTS 686P,688P,746P, Pimple Saudagar, 411027

Jun 2022
Possession
45.6%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 45.6%.

Official RERA facts

Registration
P52100018670
Status
New
Stage
Certificate Signed
Possession
June 2022originally June 2021
Construction
45.6% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Storm Water Drains60%
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Water80%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacedone

Building & registration

RERA registered
Nov 2018
Floors
7

Buyer community

Connect with other buyers and owners of VISION BOULEVARD - Phase II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VISION BOULEVARD - Phase II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.