Optima 2.0MahaRERA P52100018793
37-2-B-2-3, WADGAON BK, 411041
Dec 2026
Possession
93.2%
Built
9
Complaints
177
Units
High risk
- Possession delayed ~1 yr. Originally promised Dec 2025, now proposed Dec 2026 per the RERA filing.
- 9 RERA complaints. 9 complaint records are disclosed against this project on MahaRERA.
Official RERA facts
- Registration
- P52100018793
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally December 2025
- Construction
- 93.2% complete
- Units sold
- 163 of 177
RERA complaint record9 records
- ComplaintCC1260379019 Jun 2026Venkat Nageshrao Subbaiah Komarashetty vs M/S. SOBA ASSOCIATES
- ComplaintCC1260217313 Apr 2026Sachin Hanmantrao Jadhav vs M/S. SOBA ASSOCIATES
- ComplaintCC1260213311 Apr 2026Sanjay Lalchand Shah vs M/S. SOBA ASSOCIATES
- ComplaintCC126020789 Apr 2026Prithaviraj Shivaji Dakre vs M/S. SOBA ASSOCIATES
- ComplaintCC1260150318 Mar 2026Vaibhav Kulkarni vs M/S. SOBA ASSOCIATES
- ComplaintCC126012377 Mar 2026Darshan Shah vs M/S. SOBA ASSOCIATES
- ComplaintCC126012367 Mar 2026Nikhilesh Shah vs M/S. SOBA ASSOCIATES
- ComplaintCC1260076110 Feb 2026AKASH ARJUNE vs M/S. SOBA ASSOCIATES
- ComplaintCC1250065824 Feb 2025Rushikesh Shirish Kulkarni vs M/S. SOBA ASSOCIATES
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths50%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains50%
Landscaping & Tree Planting70%
Street Lightingnot started
Community Buildings50%
Treatment And Disposal Of Sewage And Sullage Water70%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Dec 2018
- Floors
- 19
- Unit mix
- 165 res ยท 12 comm
- Architect
- JAY AREM ARCHITECTURE & INTERIOR CONSULTANT
Buyer community
Connect with other buyers and owners of Optima 2.0 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Optima 2.0. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.