Under construction

LIFE 360 PHASE 2MahaRERA P52100018941

by SMP NAMRATA ASSOCIATES

S NO 129,130P,131P, KALEWADI, 411037

Jun 2023
Possession
50.9%
Built
2
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 50.9%.

Official RERA facts

Registration
P52100018941
Status
New
Stage
Certificate Signed
Possession
June 2023
Construction
50.9% complete
Units sold
0 of 0

RERA complaint record2 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths25%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Planting50%
Street Lightingnot started
Community Buildings80%
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacedone
Open Parkingnot started

Building & registration

RERA registered
Dec 2018
Floors
17

Buyer community

Connect with other buyers and owners of LIFE 360 PHASE 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching LIFE 360 PHASE 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.