Under construction

Trident Commercial and MHADAMahaRERA P52100019023

by PARANJAPE SCHEMES (CONSTRUCTION) LTD

55/1,55/2,55/3,56/2,57/1,57/2,57/3,57/4,60/1/1,60/1/2,60/2/1,60/2/2, Wakad, 411057

May 2023
Possession
9.1%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (May 2023) has passed with construction at 9.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2023 per the RERA filing.

Official RERA facts

Registration
P52100019023
Status
New
Stage
Certificate Signed
Possession
May 2023
Construction
9.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Dec 2018
Floors
19

Buyer community

Connect with other buyers and owners of Trident Commercial and MHADA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Trident Commercial and MHADA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.