Under construction
THE VIBEMahaRERA P52100019109
Final plot no 394 Part, Sub Plot 1, 2, Sr No 21A/10/A, Sangamwadi, Pune, Koregaon Park, 411001
Sept 2029
Possession
14%
Built
13
Complaints
0
Units
High risk
- Possession delayed ~5 yrs. Originally promised Nov 2024, now proposed Sept 2029 per the RERA filing.
- 13 RERA complaints. 13 complaint records are disclosed against this project on MahaRERA.
Official RERA facts
- Registration
- P52100019109
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2029originally November 2024
- Construction
- 14% complete
- Units sold
- 0 of 0
RERA complaint record13 records
- ComplaintCC1260395926 Jun 2026Manav Ahluwalia vs GAGAN TITANIUM SPACES LLP
- ComplaintCC1260380119 Jun 2026Kapko International vs GAGAN TITANIUM SPACES LLP
- ComplaintCC1260380419 Jun 2026Kapko International vs GAGAN TITANIUM SPACES LLP
- ComplaintCC1260380319 Jun 2026Kapko International vs GAGAN TITANIUM SPACES LLP
- ComplaintCC1260380219 Jun 2026Kapko International vs GAGAN TITANIUM SPACES LLP
- ComplaintCC1260371016 Jun 2026Habiba Sajjadhussain Gabrani vs GAGAN TITANIUM SPACES LLP
- ComplaintCC1260370916 Jun 2026Habiba Sajjadhussain Gabrani vs GAGAN TITANIUM SPACES LLP
- ComplaintCC1260371716 Jun 2026SAJJADHUSSAIN GULAMHUSAIN GABRANI vs GAGAN TITANIUM SPACES LLP
- ComplaintCC126011683 Mar 2026Shyam Vipin Sanghavi vs GAGAN TITANIUM SPACES LLP
- ComplaintCC126011673 Mar 2026Shyam Vipin Sanghavi vs GAGAN TITANIUM SPACES LLP
- ComplaintCC125030711 Sept 2025Usha Laxminarayan Agarwal vs GAGAN TITANIUM SPACES LLPOrder of Usha Agarwal vs GAGAN TITANIUM SPACES LLP.pdf on MahaRERA
- ComplaintCC1250032329 Jan 2025Suraksha Housing and Finance LLP vs GAGAN TITANIUM SPACES LLPOrder of Suraksha Housing and Finance vs Gagan Titanium.pdf on MahaRERA
- ComplaintCC00500000047125812 Jul 2024Prashant Subhash Sutar vs Gagan Titanium Spaces LLPFinal Order of Prashant Suthar 1.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Jan 2019
- Floors
- 10
Buyer community
Connect with other buyers and owners of THE VIBE โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching THE VIBE. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.