One Place - WakadMahaRERA P52100019579
S no 194, Wakad, 411057
Dec 2024
Possession
74.5%
Built
6
Complaints
49
Units
High risk
- 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 74.5%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2024 per the RERA filing.
Official RERA facts
- Registration
- P52100019579
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2024
- Construction
- 74.5% complete
- Units sold
- 47 of 49
RERA complaint record6 records
- ComplaintCC1250284013 Aug 2025Sai Mittal Associates vs Mr Kapil Babasaheb JadhavFinal 2nd Order of Sai Mittal - 2840 (1).pdf on MahaRERA
- ComplaintCC1250284113 Aug 2025Sai Mittal Associates vs Mr Kapil Babasaheb JadhavFinal 3rd Order of Sai Mittal - 2841 (1).pdf on MahaRERA
- ComplaintCC1250284213 Aug 2025Sai Mittal Associates vs Mr Kapil Babasaheb JadhavFinal 4th Order of Sai Mittal - 2842.pdf on MahaRERA
- ComplaintCC1250284313 Aug 2025Sai Mittal Associates vs Mr Kapil Babasaheb JadhavFinal Order of Sai Mittal - 2843.pdf on MahaRERA
- ComplaintCC1250243117 Jul 2025Govind Tukaram Ghadlinge vs Sai Mittal AssociatesFinal Order of Govind Gadhlingee - Withdrawal.pdf on MahaRERA
- ComplaintCC00500000025898210 Jun 2023Harshad Deshpande vs Mittal BuildersWithdrawal order 258982.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Feb 2019
- Floors
- 7
- Unit mix
- 0 res ยท 49 comm
- Architect
- Solespace
Buyer community
Connect with other buyers and owners of One Place - Wakad โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching One Place - Wakad. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.