Under construction

BHAMA AMBERMahaRERA P52100020046

by AASTHA BUILDCON

S.NO-4671,4672,4673,4674,7848, NEAR OLD POLICE STATION, 410506

Mar 2028
Possession
63.6%
Built
0
Complaints
33
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Jun 2023, now proposed Mar 2028 per the RERA filing.

Official RERA facts

Registration
P52100020046
Status
New
Stage
Certificate Signed
Possession
March 2028originally June 2023
Construction
63.6% complete
Units sold
12 of 33

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Street Lightingnot started
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Mar 2019
Floors
6
Unit mix
28 res ยท 5 comm

Buyer community

Connect with other buyers and owners of BHAMA AMBER โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BHAMA AMBER. Real notes from real buyers beat any brochure.

Start a discussion