Manor CrystalMahaRERA P52100020056

by OXFORD INFRA GROUP

S No137/2/2,Bhumkar Chowk-Karpenagar,Wakad, Pune, Mulshi, 411057

Sept 2026
Possession
56.4%
Built
7
Complaints
32
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Sept 2026 per the RERA filing.
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2026 per the RERA filing.

Official RERA facts

Registration
P52100020056
Status
New
Stage
Certificate Signed
Possession
September 2026originally December 2022
Construction
56.4% complete
Units sold
12 of 32

RERA complaint record7 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Mar 2019
Floors
6
Unit mix
32 res ยท 0 comm
Architect
unusual spaces

Buyer community

Connect with other buyers and owners of Manor Crystal โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Manor Crystal. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.