PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

VTP Belair C building

by NNP BUILDCON PVT. LTD.

SNO47/1,47/2,47/3, Mhalunge, 411045

Dec 2024
Possession
100%
Built
8
Complaints
0
Units
High risk
  • 8 RERA complaints. 8 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Swimming Pool, Sports / Jogging are at 0% build with possession due Dec 2024 per the RERA filing.

Official RERA facts

Registration
P52100020081
Status
New
Stage
Certificate Signed
Possession
December 2024
Construction
100% complete
Units sold
0 of 0

RERA complaint record8 records

  • ComplaintCC1260253030 Apr 2026
    NNP BUILDCON PVT. LTD. vs Sangita Ravindra Shinde
  • ComplaintCC1260251229 Apr 2026
    NNP BUILDCON PVT. LTD. vs AKASH ASHOK KADAM
  • ComplaintCC0050000002696763 Nov 2023
    NNP BUILDCON PRIVATE LIMITED vs CHANDAN KUMAR
    CC005_269676.pdf on MahaRERA
  • Misc. applicationCC0050000002696733 Nov 2023
    NNP BUILDCON PRIVATE LIMITED vs BHARATSINGH MEHARDAN LAKHAWAT
    CC005_269673.pdf on MahaRERA
  • Misc. applicationCC0050000002696753 Nov 2023
    NNP BUILDCON PRIVATE LIMITED vs PRADIP KUMAR SAHU through POA- Prashant Kumar Sahu
    CC005_269675.pdf on MahaRERA
  • ComplaintCC0050000002696733 Nov 2023
    NNP BUILDCON PRIVATE LIMITED vs BHARATSINGH MEHARDAN LAKHAWAT
    CC005_269673.pdf on MahaRERA
  • Misc. applicationCC0050000002696763 Nov 2023
    NNP BUILDCON PRIVATE LIMITED vs CHANDAN KUMAR
    CC005_269676.pdf on MahaRERA
  • ComplaintCC0050000002696753 Nov 2023
    NNP BUILDCON PRIVATE LIMITED vs PRADIP KUMAR SAHU through POA- Prashant Kumar Sahu
    CC005_269675.pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone
Loungenot started
Swimming Poolnot started
Multipurpose Courtnot started
Sky Walknot started

Building & registration

RERA registered
Mar 2019
Floors
27

Buyer community

Connect with other buyers and owners of VTP Belair C building โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VTP Belair C building. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.