All RERA projects
๐๏ธ
Under construction
Lodha Belmondo - Tower 30MahaRERA P52100020188
264/P, 265/P, Mawal, 412101
Dec 2026
Possession
90.9%
Built
0
Complaints
81
Units
High risk
- Possession delayed ~1 yr. Originally promised Sept 2025, now proposed Dec 2026 per the RERA filing.
- Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52100020188
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026originally September 2025
- Construction
- 90.9% complete
- Units sold
- 81 of 81
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingdone
Building & registration
- RERA registered
- Mar 2019
- Floors
- 22
- Unit mix
- 81 res ยท 0 comm
- Architect
- Pradeepmkamble and associates
Buyer community
Connect with other buyers and owners of Lodha Belmondo - Tower 30 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Lodha Belmondo - Tower 30. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.