1 Hallmark Aveneu Phase IIMahaRERA P52100020694

by RajHeramb Properties

Survey No 91 2A 2B Ravet Tal Haveli Dist Pune, Haveli, 412101

Apr 2028
Possession
40.2%
Built
0
Complaints
47
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Apr 2024, now proposed Apr 2028 per the RERA filing.

Official RERA facts

Registration
P52100020694
Status
New
Stage
Certificate Signed
Possession
April 2028originally April 2024
Construction
40.2% complete
Units sold
37 of 47

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Water90%
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingnot started
Energy managemcnt90%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
May 2019
Floors
14
Unit mix
47 res ยท 0 comm
Architect
Gem Associates

Buyer community

Connect with other buyers and owners of 1 Hallmark Aveneu Phase II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching 1 Hallmark Aveneu Phase II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.