SWARNA VATIKAMahaRERA P52100020905

by RAICHANDANI CONSTRUCTIONS AND DEVELOPERS

S No 16A/2 C T S No 668/3, PUNE, 411048

Jul 2024
Possession
93.2%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Mar 2023, now proposed Jul 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2024) has passed with construction at 93.2%.

Official RERA facts

Registration
P52100020905
Status
New
Stage
Certificate Signed
Possession
July 2024originally March 2023
Construction
93.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
May 2019
Floors
14

Buyer community

Connect with other buyers and owners of SWARNA VATIKA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.