Under construction

SUNAND APARTMENT PHASE IMahaRERA P52100021064

by ARCHWAY PROPERTIES

S. NO. 720 PLOT NO. 16 CTS NO 163, SADASHIV PETH, 411030

Dec 2022
Possession
86.8%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2022) has passed with construction at 86.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2022 per the RERA filing.

Official RERA facts

Registration
P52100021064
Status
New
Stage
Certificate Signed
Possession
December 2022
Construction
86.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting50%
Energy managemcnt50%
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station80%

Building & registration

RERA registered
May 2019
Floors
7

Buyer community

Connect with other buyers and owners of SUNAND APARTMENT PHASE I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SUNAND APARTMENT PHASE I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.