PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

DEDGAONKAR ARCADEMahaRERA P52100021263

by TRINITY FACADES PRIVATE LIMITED

C. T. S NUMBER 591 AND 592, GURUWAR PETH PUNE, 411004

Dec 2023
Possession
70.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 70.9%.

Official RERA facts

Registration
P52100021263
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
70.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths40%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jun 2019
Floors
8

Buyer community

Connect with other buyers and owners of DEDGAONKAR ARCADE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching DEDGAONKAR ARCADE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.