Under construction

NAKODA HEIGHTMahaRERA P52100021416

by AMBIKA DEVELOPERS

CTS 567, 568, 569 TAL KHED CHAKAN, MANIK CHOWK, 410501

Dec 2028
Possession
73.2%
Built
0
Complaints
42
Units
High risk
  • Possession delayed ~7 yrs. Originally promised Dec 2021, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P52100021416
Status
New
Stage
Certificate Signed
Possession
December 2028originally December 2021
Construction
73.2% complete
Units sold
3 of 42

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply65%
Sewerage (Chamber, Lines, Septic Tank , STP)55%
Landscaping & Tree Plantingnot started
Energy managemcnt35%
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station60%

Building & registration

RERA registered
Jun 2019
Floors
6
Unit mix
23 res ยท 19 comm
Architect
DEEPAK HONKAN

Buyer community

Connect with other buyers and owners of NAKODA HEIGHT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NAKODA HEIGHT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.