Grande View7 Phase VI Buiding IMahaRERA P52100022032
6/4,5,6,7,8 6/12,13,14.15, Ambegaon BK, 411046
Jun 2026
Possession
81.8%
Built
0
Complaints
56
Units
High risk
- Possession delayed ~2 yrs. Originally promised Dec 2023, now proposed Jun 2026 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 81.8%.
Official RERA facts
- Registration
- P52100022032
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2026originally December 2023
- Construction
- 81.8% complete
- Units sold
- 46 of 56
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supply98%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcnt50%
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station98%
Aggregate area of recreational Open Spacedone
Open Parkingdone
Building & registration
- RERA registered
- Aug 2019
- Floors
- 15
- Unit mix
- 56 res ยท 0 comm
- Architect
- Voussoirs Architect & interior Designers
Buyer community
Connect with other buyers and owners of Grande View7 Phase VI Buiding I โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Grande View7 Phase VI Buiding I. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.