Under construction

Godrej Hillside 2MahaRERA P52100022153

by Mahalunge Township Developers LLP

Survey No 40 and others Sector R4, Mahalunge, 411045

Oct 2024
Possession
81.8%
Built
3
Complaints
550
Units
High risk
  • Possession date passed. The proposed possession date (Oct 2024) has passed with construction at 81.8%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Oct 2024 per the RERA filing.

Official RERA facts

Registration
P52100022153
Status
New
Stage
Certificate Signed
Possession
October 2024
Construction
81.8% complete
Units sold
547 of 550

RERA complaint record3 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Sept 2019
Floors
23
Unit mix
540 res ยท 10 comm
Architect
V K a Architecture

Buyer community

Connect with other buyers and owners of Godrej Hillside 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Godrej Hillside 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.