MARUTI AMBER RESIDENCYMahaRERA P52100022749

by MARUTI INFRA

3189 93, 3189 94, SWARAJ NAGARI, 410507

Feb 2022
Possession
52.3%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Feb 2022) has passed with construction at 52.3%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Feb 2022 per the RERA filing.

Official RERA facts

Registration
P52100022749
Status
New
Stage
Certificate Signed
Possession
February 2022
Construction
52.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Open Parking80%

Building & registration

RERA registered
Oct 2019
Floors
5

Buyer community

Connect with other buyers and owners of MARUTI AMBER RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MARUTI AMBER RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.