All RERA projects
๐๏ธ
Under construction
UTKARSH HEIGHTSMahaRERA P52100023142
CTS No.966 1 Raviwar Peth, RAVIWAR PETH, 411002
Mar 2029
Possession
21.8%
Built
0
Complaints
54
Units
High risk
- Possession delayed ~3 yrs. Originally promised Mar 2026, now proposed Mar 2029 per the RERA filing.
Official RERA facts
- Registration
- P52100023142
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2029originally March 2026
- Construction
- 21.8% complete
- Units sold
- 3 of 54
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Dec 2019
- Floors
- 12
- Unit mix
- 28 res ยท 26 comm
Buyer community
Connect with other buyers and owners of UTKARSH HEIGHTS โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching UTKARSH HEIGHTS. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.