Under construction

PARITOSH DMahaRERA P52100023380

by SHARADA ALLIANCE SHELTERS

31 3A, 32 1A, 31 4, 31 3B2, BALEWADI, 411045

Nov 2023
Possession
65.5%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Nov 2023) has passed with construction at 65.5%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Nov 2023 per the RERA filing.

Official RERA facts

Registration
P52100023380
Status
New
Stage
Certificate Signed
Possession
November 2023
Construction
65.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths75%
Water Supply75%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains75%
Landscaping & Tree Planting50%
Street Lighting50%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposal80%
Water conservation /Rain water harvesting80%
Fire protection and fire safety requirements75%
Electrical meter room, sub-station, receiving station75%
Aggregate area of recreational Open Space50%
Open Parking50%

Building & registration

RERA registered
Dec 2019
Floors
18

Buyer community

Connect with other buyers and owners of PARITOSH D โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PARITOSH D. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.