Under construction

BA Swadesha- Phase 1MahaRERA P52100024275

by Spectrum Realty

Gat No 231 P Old Gat No 1349 P Moshi Borhadewadi, Moshi Borhadewadi, 412105

Dec 2023
Possession
71.4%
Built
1
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 71.4%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2023 per the RERA filing.

Official RERA facts

Registration
P52100024275
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
71.4% complete
Units sold
0 of 0

RERA complaint record1 record

  • ComplaintCC00500000025922429 Jul 2023
    AVINASH VISHNU WAGHMARE vs PANKAJ LAKHAMSI PATEL

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Internal Roads & Footpathsnot started
Internal Roads & Footpathsnot started
Water Supplynot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Street Lightingnot started
Community Buildingsnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Aggregate area of recreational Open Spacenot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Open Parkingnot started

Building & registration

RERA registered
Jan 2020
Floors
15

Buyer community

Connect with other buyers and owners of BA Swadesha- Phase 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching BA Swadesha- Phase 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.