PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

43 Privet Drive- C BuildingMahaRERA P52100025169

by S S Properties

S.NO.43H.NO,8,9,10,11,12A, 12B, 13/1,2, 14/1,2, 44 8/1 Balewadi, Balewadi, 411045

Dec 2023
Possession
70%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 70%.

Official RERA facts

Registration
P52100025169
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
70% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths20%
Water Supply83%
Sewerage (Chamber, Lines, Septic Tank , STP)67%
Storm Water Drains50%
Landscaping & Tree Planting50%
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water67%
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting50%
Energy managemcntnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacedone
Open Parking80%
Gate and compound wall75%

Building & registration

RERA registered
Mar 2020
Floors
22

Buyer community

Connect with other buyers and owners of 43 Privet Drive- C Building โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching 43 Privet Drive- C Building. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.