MANTRA INSIGNIA PHASE 3 RESIDENCIALMahaRERA P52100026580

by MANTRA INSIGNIA LLP

SR, NO.9 TO 14 PL NO.1/54 1/55, MUNDWA, 411036

Jun 2025
Possession
96.4%
Built
1
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 96.4%.

Official RERA facts

Registration
P52100026580
Status
New
Stage
Certificate Signed
Possession
June 2025
Construction
96.4% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingdone

Building & registration

RERA registered
Oct 2020
Floors
24

Buyer community

Connect with other buyers and owners of MANTRA INSIGNIA PHASE 3 RESIDENCIAL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MANTRA INSIGNIA PHASE 3 RESIDENCIAL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.