Under construction

MY HOME KIWALEMahaRERA P52100026833

by RAVET LAND DEVELOPERS LLP

S NO 8 1 7, 8 1 8 & 8 1 9 village Kiwale Tal Mulshi Dist Pune, KIWALE, 412101

Apr 2026
Possession
63.6%
Built
3
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Apr 2026) has passed with construction at 63.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2026 per the RERA filing.

Official RERA facts

Registration
P52100026833
Status
New
Stage
Certificate Signed
Possession
April 2026
Construction
63.6% complete
Units sold
0 of 0

RERA complaint record3 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths30%
Water Supply30%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains70%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildings50%
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Oct 2020
Floors
16

Buyer community

Connect with other buyers and owners of MY HOME KIWALE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MY HOME KIWALE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.