PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SWASTIK PEARLMahaRERA P52100027178

by SWASTIK BUILDERS

35, TALEGAON DABHADE, 410506

Nov 2024
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2022, now proposed Nov 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Nov 2024) has passed with construction at 90.9%.

Official RERA facts

Registration
P52100027178
Status
New
Stage
Certificate Signed
Possession
November 2024originally December 2022
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Nov 2020
Floors
5

Buyer community

Connect with other buyers and owners of SWASTIK PEARL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SWASTIK PEARL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.