All RERA projects
๐๏ธ
Under construction
VRINDAVAN PARKMahaRERA P52100027482
SR. NO. 6A/1/6, NEWGAT NO. 291, KADAMWAK WASTI, 412201
Apr 2027
Possession
43%
Built
0
Complaints
54
Units
High risk
- Possession delayed ~2 yrs. Originally promised Jun 2025, now proposed Apr 2027 per the RERA filing.
- Behind schedule. Possession is due Apr 2027 but construction is only at 43%.
Official RERA facts
- Registration
- P52100027482
- Status
- New
- Stage
- Certificate Signed
- Possession
- April 2027originally June 2025
- Construction
- 43% complete
- Units sold
- 19 of 54
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths40%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Landscaping & Tree Planting20%
Street Lighting30%
Water conservation /Rain water harvesting40%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Dec 2020
- Floors
- 5
- Unit mix
- 48 res ยท 6 comm
- Architect
- ATIT ADMULWAR
Buyer community
Connect with other buyers and owners of VRINDAVAN PARK โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching VRINDAVAN PARK. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.