PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

THE EVOQMahaRERA P52100027486

by FUTURISTIC HOMES

129 1 B 11, 129 1 B 13 , 129 1 B 14, ASHOK THEATRE, 411017

Jun 2023
Possession
81.8%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2023 per the RERA filing.

Official RERA facts

Registration
P52100027486
Status
New
Stage
Certificate Signed
Possession
June 2023
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Dec 2020
Floors
7

Buyer community

Connect with other buyers and owners of THE EVOQ โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching THE EVOQ. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.