PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Aditya Vivaaz Project TwoMahaRERA P52100027615

by ADITYA PROMOTERS

Sur. no.92 Part RAVET, Ravet, 412101

Oct 2025
Possession
18.2%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Oct 2025) has passed with construction at 18.2%.

Official RERA facts

Registration
P52100027615
Status
New
Stage
Certificate Signed
Possession
October 2025
Construction
18.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)85%
Storm Water Drains50%
Landscaping & Tree Planting50%
Street Lightingnot started
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacedone

Building & registration

RERA registered
Dec 2020
Floors
16

Buyer community

Connect with other buyers and owners of Aditya Vivaaz Project Two โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Aditya Vivaaz Project Two. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.