All RERA projects
๐๏ธ
Under construction
NEXUS GULMOHAR WING DEFGMahaRERA P52100027744
543/1 546/2, CHARHOLI, 412105
Jun 2024
Possession
81.4%
Built
0
Complaints
380
Units
High risk
- Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 81.4%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2024 per the RERA filing.
Official RERA facts
- Registration
- P52100027744
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2024
- Construction
- 81.4% complete
- Units sold
- 331 of 380
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths80%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Jan 2021
- Floors
- 15
- Unit mix
- 380 res ยท 0 comm
Buyer community
Connect with other buyers and owners of NEXUS GULMOHAR WING DEFG โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching NEXUS GULMOHAR WING DEFG. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance