24K Stargaze - J BuildingMahaRERA P52100027791

by KOLTE-PATIL DEVELOPERS LIMITED

76P, 77P, 78P, 79P, 80P, 81P, 82P, 83P, 84P, 85P, 86P, 87P, 88P, 89P, 90P, 91P, Bavdhan, 411021

Jun 2024
Possession
90.9%
Built
1
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2024) has passed with construction at 90.9%.

Official RERA facts

Registration
P52100027791
Status
New
Stage
Certificate Signed
Possession
June 2024
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supply98%
Sewerage (Chamber, Lines, Septic Tank , STP)98%
Storm Water Drains95%
Landscaping & Tree Planting85%
Street Lighting90%
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Water95%
Solid Waste Management And Disposal95%
Water conservation /Rain water harvesting90%
Energy managemcnt90%
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station85%
Aggregate area of recreational Open Space80%
Open Parking90%

Building & registration

RERA registered
Jan 2021
Floors
13

Buyer community

Connect with other buyers and owners of 24K Stargaze - J Building โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching 24K Stargaze - J Building. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.