Under construction

YashONE Infinitee - Phase I

by Vilas Javdekar Infinitee Developers Pvt. Ltd.

S no 21 / 7 and S No 21/8, Near Puneville Project, 411033

Jun 2025
Possession
96.4%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2025) has passed with construction at 96.4%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2025 per the RERA filing.

Official RERA facts

Registration
P52100028229
Status
New
Stage
Certificate Signed
Possession
June 2025
Construction
96.4% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths70%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)75%
Storm Water Drains75%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvesting50%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Space70%

Building & registration

RERA registered
Feb 2021
Floors
25

Buyer community

Connect with other buyers and owners of YashONE Infinitee - Phase I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching YashONE Infinitee - Phase I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.