๐Ÿ—๏ธ
Under construction

EPIC PHASE - 3MahaRERA P52100028703

by Shivsagar Promoters & Developers

Gat No. 1102 Part, Wagholi, 412207

Jun 2026
Possession
89.5%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 89.5%.

Official RERA facts

Registration
P52100028703
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
89.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths95%
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains90%
Landscaping & Tree Planting80%
Street Lighting60%
Treatment And Disposal Of Sewage And Sullage Water60%
Water conservation /Rain water harvesting80%
Energy managemcnt80%
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station95%
Aggregate area of recreational Open Space90%
Open Parking90%
Swimming Pool90%

Building & registration

RERA registered
Mar 2021
Floors
11

Buyer community

Connect with other buyers and owners of EPIC PHASE - 3 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching EPIC PHASE - 3. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.