Under construction

VISION FLORAMahaRERA P52100029188

by Siddhivinayak Namrata Developers

83/1 83/2 84/3 84/4 85/2 85/3 CTS No 757 to760 732 to 734 739 to 742 752 761 1097, Pimple Saudagar, 411027

Apr 2026
Possession
18.2%
Built
2
Complaints
102
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Apr 2024, now proposed Apr 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Apr 2026) has passed with construction at 18.2%.

Official RERA facts

Registration
P52100029188
Status
New
Stage
Certificate Signed
Possession
April 2026originally April 2024
Construction
18.2% complete
Units sold
73 of 102

RERA complaint record2 records

  • ComplaintCC1260169325 Mar 2026
    Siddhivinayak Namrata Developers vs Mrs Sunayana Jaiswal
  • ComplaintCC1260139813 Mar 2026
    Siddhivinayak Namrata Developers vs Mrs Sunayana Jaiswal

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
May 2021
Floors
9
Unit mix
0 res ยท 102 comm
Architect
VK A Architecture

Buyer community

Connect with other buyers and owners of VISION FLORA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VISION FLORA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.