Under construction

VTP SIERRA PHASE-2MahaRERA P52100029394

by PRASANNA DEVELOPERS

S. NO. 4 (PART), 43/1, 44/1, 44/2, 45/1, 45/2, 46/1, 46/2, 7 (PART), Mulshi, 411021

Dec 2026
Possession
98.2%
Built
9
Complaints
361
Units
High risk
  • 9 RERA complaints. 9 complaint records are disclosed against this project on MahaRERA.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52100029394
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2025
Construction
98.2% complete
Units sold
354 of 361

RERA complaint record9 records

  • ComplaintCC1260401828 Jun 2026
    Shrishail Mahanad vs PRASANNA DEVELOPERS
  • ComplaintCC1260395025 Jun 2026
    Rahul Verma vs PRASANNA DEVELOPERS
  • ComplaintCC126034213 Jun 2026
    Avinash Purushottam Khadse vs PRASANNA DEVELOPERS
  • ComplaintCC1260307423 May 2026
    Vishal Kumar vs PRASANNA DEVELOPERS
  • ComplaintCC1260300021 May 2026
    Rohit Sahebrao Surwase vs PRASANNA DEVELOPERS
  • ComplaintCC126019442 Apr 2026
    Rohan Atul Gondkar vs PRASANNA DEVELOPERS
  • ComplaintCC126000997 Jan 2026
    Pranav Jagannath Mahajan vs PRASANNA DEVELOPERS
  • Misc. applicationCC00500000047150412 Aug 2024
    Prasanna Developers vs KRUSHNA PRALHADRAO SHINDE
  • ComplaintCC00500000047150412 Aug 2024
    Prasanna Developers vs KRUSHNA PRALHADRAO SHINDE
    Sr 24 PRASANNA DEVELOPERS REVISED CC005000000471504.pdf on MahaRERA

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths78%
Water Supply52%
Sewerage (Chamber, Lines, Septic Tank , STP)55%
Storm Water Drains58%
Landscaping & Tree Planting30%
Street Lighting20%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Water72%
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting35%
Energy managemcnt30%
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station56%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
May 2021
Floors
31
Unit mix
356 res ยท 5 comm
Architect
VK design & projects Pvt. Ltd.

Buyer community

Connect with other buyers and owners of VTP SIERRA PHASE-2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VTP SIERRA PHASE-2. Real notes from real buyers beat any brochure.

Start a discussion