TIME CITYMahaRERA P52100029707

by SUDHIR MARUTI NARAWADE

S NO 2619 1A 1 2619 1A 2 at Ale, Alephata, 412411

Dec 2027
Possession
24.2%
Built
0
Complaints
52
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Apr 2024, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52100029707
Status
New
Stage
Certificate Signed
Possession
December 2027originally April 2024
Construction
24.2% complete
Units sold
2 of 52

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jun 2021
Floors
18
Unit mix
52 res ยท 0 comm

Buyer community

Connect with other buyers and owners of TIME CITY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching TIME CITY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.