All RERA projects
๐๏ธ
Under construction
Hirals Breeze
by Mangaldeep Associates & Developers
Sr No. 111/3/7, 111/3/8 CTS No. 7248, Rahatani, 411017
Dec 2024
Possession
72.7%
Built
0
Complaints
10
Units
Caution
- Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 72.7%.
Official RERA facts
- Registration
- P52100029974
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2024originally December 2023
- Construction
- 72.7% complete
- Units sold
- 6 of 10
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Street Lightingnot started
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationdone
Building & registration
- RERA registered
- Jul 2021
- Floors
- 7
- Unit mix
- 10 res ยท 0 comm
- Architect
- Sachin Sutar
Buyer community
Connect with other buyers and owners of Hirals Breeze โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Hirals Breeze. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.