ORCHIDMahaRERA P52100030694
18/4B , 19/2, 19/3/1, DHANORI, 411015
- Possession date passed. The proposed possession date (Aug 2023) has passed with construction at 81.8%.
Official RERA facts
- Registration
- P52100030694
- Status
- New
- Stage
- Certificate Signed
- Possession
- August 2023
- Construction
- 81.8% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Sept 2021
- Floors
- 7
- Plot / CTS / survey no.
- 18/4B , 19/2, 19/3/1
- Planning authority
- Others
- Approved layout land
- 464.5 sq.m
- Land for this registration
- 464.5 sq.m
- Permissible built-up area
- 1,480 sq.m
- Registered office
- DREAM MAX BUILDING
- North
- BY COMPOUND WALL
- South
- BY 9MTR WIDE ROAD
- East
- OPEN SPACE
- West
- BY PLOT NO A-2
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- ICICI BANK LIMITED โ 65808IFSC ICIC0003977TRUPATI KASHI GANGA DHANORI PUNE 15
Commencement Certificate documents
- NA.pdf
- new ccc_compressed (1).pdf
Buyer community
Connect with other buyers and owners of ORCHID โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching ORCHID. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.