PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

YashONE Infinitee - Phase III

by Vilas Javdekar Infinitee Developers Pvt. Ltd.

21/7 and 21/8 Part, Kate wasti, 411033

Dec 2025
Possession
86.8%
Built
0
Complaints
150
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 86.8%.

Official RERA facts

Registration
P52100030825
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
86.8% complete
Units sold
144 of 150

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths60%
Water Supply75%
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Storm Water Drains90%
Landscaping & Tree Planting50%
Street Lighting60%
Treatment And Disposal Of Sewage And Sullage Water90%
Solid Waste Management And Disposal90%
Water conservation /Rain water harvesting90%
Energy managemcntnot started
Fire protection and fire safety requirements60%
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Space50%
Open Parkingnot started

Building & registration

RERA registered
Sept 2021
Floors
14
Unit mix
104 res ยท 46 comm
Architect
Neha Bagayatkar

Buyer community

Connect with other buyers and owners of YashONE Infinitee - Phase III โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching YashONE Infinitee - Phase III. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.