41 CITY HUBMahaRERA P52100030903

by M/s WONDER SKYLINE LLP

SR NO 224 HISSA NO 2 1 2 2 AND SR NO 226A HISSA NO 1 1, 1 2, 1 3, 1 4, 1 5, HADAPSAR, 411028

Mar 2027
Possession
90.5%
Built
1
Complaints
285
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Nov 2024, now proposed Mar 2027 per the RERA filing.

Official RERA facts

Registration
P52100030903
Status
New
Stage
Certificate Signed
Possession
March 2027originally November 2024
Construction
90.5% complete
Units sold
244 of 285

RERA complaint record1 record

  • ComplaintCC1240111413 Dec 2024
    CHETAN NANDKISHOR NOGAJA vs M/s WONDER SKYLINE LLP

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started

Building & registration

RERA registered
Sept 2021
Floors
16
Unit mix
0 res ยท 285 comm
Architect
CUBIX ARCHITECTS ASSOCIATES

Buyer community

Connect with other buyers and owners of 41 CITY HUB โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching 41 CITY HUB. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.