Under construction

The leaf Phase IV Building-04 Wing I,JMahaRERA P52100031729

by SHREE PUSHKAR DEVELOPERS

35, Pune, 411048

Dec 2024
Possession
99.3%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Dec 2023, now proposed Dec 2024 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 99.3%.

Official RERA facts

Registration
P52100031729
Status
New
Stage
Certificate Signed
Possession
December 2024originally December 2023
Construction
99.3% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lighting80%
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Nov 2021
Floors
16

Buyer community

Connect with other buyers and owners of The leaf Phase IV Building-04 Wing I,J โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching The leaf Phase IV Building-04 Wing I,J. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.