Under construction

PARK CONNECT PHASE IIMahaRERA P52100031776

by PRIDE PURPLE INFRASTRUCTURE

S NO 40 41 51 44, MARUNJI, 411057

Dec 2024
Possession
72.2%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 72.2%.

Official RERA facts

Registration
P52100031776
Status
New
Stage
Certificate Signed
Possession
December 2024
Construction
72.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths55%
Water Supply55%
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains50%
Landscaping & Tree Planting50%
Street Lighting50%
Community Buildings60%
Treatment And Disposal Of Sewage And Sullage Water70%
Solid Waste Management And Disposal50%
Water conservation /Rain water harvesting50%
Fire protection and fire safety requirements10%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Nov 2021
Floors
19

Buyer community

Connect with other buyers and owners of PARK CONNECT PHASE II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PARK CONNECT PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.