Under construction

NIVASA ELEVIA - PHASE IMahaRERA P52100031816

by Shree Samarth Spaces

SR NO 9 TO 14 1 68, KESHAVNAGAR, 411036

Dec 2025
Possession
60%
Built
1
Complaints
140
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 60%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2025 per the RERA filing.

Official RERA facts

Registration
P52100031816
Status
New
Stage
Certificate Signed
Possession
December 2025originally December 2024
Construction
60% complete
Units sold
114 of 140

RERA complaint record1 record

  • ComplaintCC126007137 Feb 2026
    Nishant S Narad vs Shree Samarth Spaces

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains80%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Water70%
Solid Waste Management And Disposal70%
Water conservation /Rain water harvesting50%
Energy managemcnt50%
Fire protection and fire safety requirements30%
Electrical meter room, sub-station, receiving station70%
Open Parkingnot started

Building & registration

RERA registered
Nov 2021
Floors
16
Unit mix
140 res ยท 0 comm
Architect
ANKUR ASSOCIATES

Buyer community

Connect with other buyers and owners of NIVASA ELEVIA - PHASE I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NIVASA ELEVIA - PHASE I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.