PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

30 DRIVEMahaRERA P52100032106

by Duville Estates Private Limited

17/1, PUNE, 411001

May 2024
Possession
90.9%
Built
0
Complaints
0
Units
High risk
  • Litigation pending (5). MahaRERA's litigation disclosure lists 5 pending cases against this project.
  • Possession date passed. The proposed possession date (May 2024) has passed with construction at 90.9%.

Official RERA facts

Registration
P52100032106
Status
New
Stage
Certificate Signed
Possession
May 2024originally November 2023
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Litigation record5 cases

  • Pune Civil CourtCase 48/2016/2016
    Pending
  • Court of Civil Judge Senior Division PuneCase 1774/2015/2015
    Dismissed by Honble District and Sessions Court Pune
    Status: Closed
  • Court of Civil Judge Senior Division PuneCase 226/2015/2015
    Pending
    Status: Ongoing
  • Court of civil Judge SEnior Division PuneCase 597/2015/2015
    Pending
    Status: Ongoing
  • Court of Civil Judge Senior Division PuneCase 226/2015
    Pending
    Status: Ongoing

Possession extension history

  • EXT52100025013Revised to May 2024

    During the covid-19 pandemic period the works in the said Project has got delayed due to inadequate manpower and difficulty in re-mobilisation of resources. As a result of which, we have received the Occupancy Certificates of the after expiry of the validity of the said Project. You are requested to the note that, we have completed the construction of the said Project and possession of units has already been delivered to the Allottees. We have uploaded Form-4 (Completion Certificate) dated 30th September, 2024 on MahaRERA portal, but the same was rejected due to expiry of validity of the said Project. Therefore, we have made this application for extension of validity of the said Project from 1st December, 2023 to 6th May, 2024 (i.e., upto the date of Final Occupancy Certificate). In case the validity of the said Project is extended by MahaRERA, the same shall not affect/jeopardize the rights of the allottees. We request you to consider the aforesaid facts and allow extension of validity of the said Project till 6th May, 2024 (i.e., upto the date of Final Occupancy Certificate) to enable us to upload Form 4 and do other relevant compliances. As per Accomodation Reservation Policy we have reserved built-up area of Plot D for PH/HDH-16 reservation. Such built-up area is to be transferred free of cost to the Pune Municipal Corporation in the form of residential apartments. Therefore, in terms of aforesaid Accommodation Reservation Policy, we have constructed residential apartments on the upper floors of the said Project, which we have transferred to the PMC free of cost. Since, the residential apartments constructed in the said Project were to be handed over to PMC free of cost and not sold in the open market, we have not uploaded the same of MahaRERA Portal. A copy of Agreement entered into with PMC for transfer of such residential apartments in the said Project is uploaded herewith as annexure, for your reference. we have also uploaded the Form-B with proposed extended date of Completion duly notarised

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Street Lightingdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone

Building & registration

RERA registered
Dec 2021
Floors
11
Plot / CTS / survey no.
17/1
Planning authority
Pune Municipal Authority
Approved layout land
1,653 sq.m
Land for this registration
1,653 sq.m
Recreational open space
165.3 sq.m
Permissible built-up area
2,790.3 sq.m
Registered office
Sopan Baug
Plot boundaries
North
30 MTR ROAD
South
NYATI EMPERIA
East
NYATI ELYSIA
West
BAIG VASTI
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • HDFC BANK โ€” 48531
    IFSC HDFC0000060
    FORT, MUMBAI

Commencement Certificate documents

  • Commencement Cert.pdf

Buyer community

Connect with other buyers and owners of 30 DRIVE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching 30 DRIVE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.