Kuber Park Phase-IMahaRERA P52100032227

by Bhujbal Buildcon

300/2/A/3/B/2/B/3, Shirur, 412210

Oct 2026
Possession
100%
Built
0
Complaints
28
Units
Caution
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Oct 2026 per the RERA filing.

Official RERA facts

Registration
P52100032227
Status
New
Stage
Certificate Signed
Possession
October 2026originally December 2023
Construction
100% complete
Units sold
28 of 28

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started

Building & registration

RERA registered
Dec 2021
Floors
6
Unit mix
28 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Kuber Park Phase-I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Kuber Park Phase-I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.