Kumar Palladium PlazaMahaRERA P52100032535

by GAGAN GLOBAL DEVELOPERS

1331, Near D cathlon Showroom, 412207

Dec 2029
Possession
80.2%
Built
0
Complaints
261
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2025, now proposed Dec 2029 per the RERA filing.

Official RERA facts

Registration
P52100032535
Status
New
Stage
Certificate Signed
Possession
December 2029originally December 2025
Construction
80.2% complete
Units sold
157 of 261

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting65%
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Water80%
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirements95%
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jan 2022
Floors
5
Unit mix
0 res ยท 261 comm
Architect
A DESIGN STUDIO Ar Mangesh Gotal
Public authority
PMRDA

Buyer community

Connect with other buyers and owners of Kumar Palladium Plaza โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Kumar Palladium Plaza. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.