RAHEJA STERLING - TOWER 1MahaRERA P52100032839

by CAVALCADE PROPERTIES PVT LTD

42/5 AND OTHERS, OFF NIBM ROAD, 411060

Mar 2026
Possession
90.9%
Built
0
Complaints
88
Units
Caution
  • Possession date passed. The proposed possession date (Mar 2026) has passed with construction at 90.9%.

Official RERA facts

Registration
P52100032839
Status
New
Stage
Certificate Signed
Possession
March 2026
Construction
90.9% complete
Units sold
86 of 88

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting95%
Street Lightingdone
Community Buildingsdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station75%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Feb 2022
Floors
26
Unit mix
88 res ยท 0 comm

Buyer community

Connect with other buyers and owners of RAHEJA STERLING - TOWER 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching RAHEJA STERLING - TOWER 1. Real notes from real buyers beat any brochure.