PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Marvel Selva Ridge Villa 6, 9, 11, 12MahaRERA P52100032968

by Marvel Selva Ridge Villa 6, 9, 11, 12

S. No. 46, Haveli, 411021

Dec 2026
Possession
46.1%
Built
0
Complaints
0
Units
Caution
  • Behind schedule. Possession is due Dec 2026 but construction is only at 46.1%.

Official RERA facts

Registration
P52100032968
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
46.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supply65%
Sewerage (Chamber, Lines, Septic Tank , STP)65%
Storm Water Drains50%
Landscaping & Tree Planting55%
Street Lighting10%
Community Buildings30%
Treatment And Disposal Of Sewage And Sullage Water30%
Solid Waste Management And Disposal80%
Water conservation /Rain water harvesting80%
Energy managemcnt80%
Fire protection and fire safety requirements75%
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Space75%

Building & registration

RERA registered
Feb 2022
Floors
6

Buyer community

Connect with other buyers and owners of Marvel Selva Ridge Villa 6, 9, 11, 12 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Marvel Selva Ridge Villa 6, 9, 11, 12. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.